Customer made strategic decision to close its manufacturing plant in Romania and relocate the production of those products to plants in Czech, Poland, Italy, Turkey, Morocco.
Quantity of part numbers, T1 customer locations and OEM brands involved with the need to deliver the transition in short timing drove significant complexity that required additional execution resources to support the project.
The nature of the work included coordination and communication with all 71 Tier 1 customer locations, sharing transfer timing, part numbers, samples , PPAP submissions and delivering new purchase orders to support the changeover in the new Sage manufacturing plants.
The Solution
Jigsaw provided a Program management resource team integrated as part of the Sage team to lead all T1 communications and support the various OEM brand approval meetings.
Using the planning and execution skills from our Consultancy business we were able to efficiently manage and track status of the part numbers with each T1 and lead all T1 project status reviews and support sage internal reviews.
Provided Sage leadership with monthly progress reports across the entire project and highlighted potential risks and opportunities with the various customers.
Why Jigsaw Business Group?
Unrivalled sector knowledge and technical expertise with an ability to look at things from a fresh perspective to deliver process driven solutions that help businesses to reduce costs, increase efficiencies and streamline business operations;
A progressive company delivering premium level support services working in strict adherence with robust in-house best practices in accordance with all industry standards.
Key Achievements
Overall scope included coordination of 532 part numbers across 71 Tier 1 customer locations (globally) involving 19 different OEM brands.
110 part numbers were confirmed through process as stock build until EOP from the current manufacturing plant.
Of 422 part numbers to transfer to new manufacturing plants, 401 were transferred with T1 agreement and new PO in place (95%) at the handover date.
Remaining 21 PO’s and transfers were taken over by the internal Sage team to manage.
Customer made strategic decision to close its manufacturing plant in Romania and relocate the production of those products to plants in Czech, Poland, Italy, Turkey, Morocco.
Quantity of part numbers, T1 customer locations and OEM brands involved with the need to deliver the transition in short timing drove significant complexity that required additional execution resources to support the project.
The nature of the work included coordination and communication with all 71 Tier 1 customer locations, sharing transfer timing, part numbers, samples , PPAP submissions and delivering new purchase orders to support the changeover in the new Sage manufacturing plants.
Jigsaw provided a Program management resource team integrated as part of the Sage team to lead all T1 communications and support the various OEM brand approval meetings.
Using the planning and execution skills from our Consultancy business we were able to efficiently manage and track status of the part numbers with each T1 and lead all T1 project status reviews and support sage internal reviews.
Provided Sage leadership with monthly progress reports across the entire project and highlighted potential risks and opportunities with the various customers.
Unrivalled sector knowledge and technical expertise with an ability to look at things from a fresh perspective to deliver process driven solutions that help businesses to reduce costs, increase efficiencies and streamline business operations;
A progressive company delivering premium level support services working in strict adherence with robust in-house best practices in accordance with all industry standards.
Overall scope included coordination of 532 part numbers across 71 Tier 1 customer locations (globally) involving 19 different OEM brands.
110 part numbers were confirmed through process as stock build until EOP from the current manufacturing plant.
Of 422 part numbers to transfer to new manufacturing plants, 401 were transferred with T1 agreement and new PO in place (95%) at the handover date.
Remaining 21 PO’s and transfers were taken over by the internal Sage team to manage.
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.